If an inventory-tracked (pool-tracked) item reserved for a project is not yet staged for installation, you can unreserve it from the current project and reserve it for another.
You can unreserve inventory-tracked items in the Inventory Pools mode in two ways:
#1 Within the project
Here, you can unreserve multiple inventory-tracked items from a project at once.
1/ Go to the Project details view.
2/ Click the 3-dot menu next to the project number at the top left corner and click “Project inventory items.”
This will open a modal with all inventory-tracked items in the project.
3/ Click the 3-dot menu of an inventory-tracked item and click “Unreserve.”
4/ Specify the quantity you want to unreserve and click “Unreserve.”
#2 From the item’s side panel
You can view an inventory-tracked item and unreserve it for multiple projects simultaneously.
1/ Go to the “Inventory.”
2/ Click the inventory-tracked item you want to unreserve.
This will open its side panel.
3/ Hover over the “Allocated” tile, and you will see the “Unreserve for projects” button.
4/ Click the button. This will open a modal listing all projects for which this item is reserved.
5/ Specify the quantity of the item you want to unreserve in the row of the project.
6/ Click “Unreserve.”